Update with any date or time-stamp

Priority
Description Time Estimate
Time Remaining
Actual Time
Last Updated By
Status
1
Test Driven Experimentation
2
0
2
Chris & Eugene
Complete
2
Input Widget
3
0
2
Chris & Eugene
Complete
3
Format Validation 2
0
.5
Chris & Eugene
Complete
4
Write Tests
2
0
2
Chris & Eugene
Complete
5
Resolving Issues (refactoring)
2
0
3
Chris & Eugene
Complete
     
     
Total   11
0
9.5
 